Shopping Cart
0 item(s) in cart
Ignou MBA Solved Assignments
Email or call us for IGNOU MBA Solved Assignments
MS-05 Solved Assignment

MS-05 Solved Assignment

Rs. 200.00  Rs. 100.00
Save: 50% off

  • Version: 2023 Jan - June



Soft Copy: Yes
Downloadable File: Yes
University: IGNOU
Course: Master of Business Administration
File: PDF/ZIP

Q&A of Ignou Mba MS-05 Solved Assignment 2023 - Management of Machines and Materials

Q. "Depending upon the focus of layout design there are some basic or classical types of Layouts." Explain, in view of the statement, the types of plant layouts.

Answer. .....

Q. "The firm has to take into consideration both the technology of production and the social aspects of the work environment." Comment on the statement.

Answer. ......

Q. What do you understand by mass production system? Explain the features of the mass production system.

Answer. ......

Q. Explain the concept of value engineering. Also, explain the various phases involved in the value engineering process.

Answer. .......

Q. "A purchase requisition is the primary and authorization document describing the needed items." Comment on the statement. Also, explain the three most common types of requisition forms.

Answer. .......

Product Details: MS-05 Solved Assignment 2023

Course: IGNOU MBA (Master of Business Administration)
Session: Jan - June 2023 July - Dec
Subject: Management of Machines and Materials

Ignou Mba MS-05 Assignments - Old Sample Answers

Q. Write a short note on Job design.
Answer. Job design involves deciding on the content of jobs, that is, the responsibilities, duties or tasks that should be grouped together in a single job. This means analysing the overall task which the team exists to achieve in order to establish the activities that need to be carried out, and dividing these activities between the members of the team................. Deciding on the content of a job starts from work requirements because that is why the job exists. When the tasks to be done have been determined it is then necessary to consider how the jobs can be set up to provide the maximum degree of intrinsic motivation for those who have to carry them out with a view to improving performance and productivity........... The elements of job design fall into three categories: an analysis of the tasks included in the job, employee requirements, and the environment in which the job takes place. These categories address the questions of how the job is performed, who does it, and where it is done.......

Q. What are the major techniques of work measurement?
Answer. Work measurement is the application of techniques designed to establish the time for an average worker to carry out a specified........ There are various ways in which work may be measured and a variety of techniques have been established......

Historical Times: One of the popular low-cost way to determine workplace productivity is by historical times. In this technique, production records and timecards are examined to find out how long a task had taken to complete previously. Though the data is easily recovered, it is not regarded as objective and is not a suggested way to measuring tasks. People, equipment and other work factors have a tendency to change even over short periods of time.

Workplace Sampling: Work or activity sampling is dependant on the postulation that the best predictor of future practice is observed behavior under analogous conditions. This type of tests need the subject to undertake tasks comparable to those accomplished on the job. Work sample tests utilize equipment that is the same or considerably like the actual equipment employed to perform a particular task. Under a small business environment, this may range from the use of a particular software program on the job..... to get help for Ignou Mba ms-05 solved assignment 2023 Jan - June or July - Dec email or call us.

Q. Write a note on PERT and CPM in project management.
Answer. Project Evaluation Review Technique and Critical Path Method (CPM) are scheduling techniques employed to plan, schedule, budget and control the numerous activities connected with projects. Projects are often huge, sophisticated, custom products which incorporate many interrelated activities to be performed either concurrently or sequentially. The planning horizon for PERT/CPM usually stretches beyond the six-month time frame of traditional short-range planning utilized in the other production processes. Utilizing PERT/CPM requires splitting the total project into a number of individual activities with identifiable time requirements. Each activity needs to be completed as part of the total work to be done.

Both CPM and PERT (Program Evaluation and Review Technique) provide the user with project management tools to plan, monitor, and update their project as it progresses. There are several similarities and differences between the two, however.


About Us    Privacy Policy    Shipping/Cancellation/Refund Policy    Terms and Conditions    Site map

Copyright © 2024 Universal Teacher Publications - IGNOU MBA Assignments, IGNOU MBA Solved Papers, Question Bank, Notes, Case Studies